Procurement steps in INGOs

Q: Write down start-to-end procurement steps in INGOs.

Normally, program staff prepares a purchase requisition and sends it to the budget manager. Once approved, it is sent to the procurement department, the steps in below:

  • Approved purchase requisition.

  • Check specifications, budget code, etc. If not, send it back to the Program. If found ok then,

  • Determine the procurement methods

  • Issue an RFQ/RFP/EOI to the enlisted vendor or open add based on the procurement methods.

  • Open quotation in the presence of the purchasing/procurement committee (PC).

  • PC members sign on each quotation.

  • Prepare Comparative statement (CS)/ Bid analysis.

  • Conduct PC meetings and get recommendations.

  • Prepare PC meeting minutes and PC member sign.

  • Select a vendor.

  • Vendor screening through SAM/OFAC/UN Search

  • Issue Purchase Order (PO).

  • Start follow-up with the vendor to ensure on-time delivery

  • Received goods or services and ensured GRN (delivery and quality) from the requestor.

  • Collect challan.

  • Collect invoices and bank details.

  • Check VAT challan.  

  • Submits finance for Process for payment.

     